Pile integrity test
Foundations provide support for structures, transferring their load to layers of soil or rock that have sufficient bearing capacity and suitable settlement characteristics to support them.
Pile foundations are deep foundations. They are formed by long, slender, columnar elements typically made from steel or reinforced concrete, or sometimes timber. A foundation is described as 'piled' when its depth is more than three times its breadth.
While the integrity of superstructure members can be tested and assessed from visual examinations, dimensions checks and so on, pile foundations, once they are in place, can be more difficult to test. Flaws and defects may develop during construction or subsequent excavation and trimming.
Pile integrity testing is used to discover and assess flaws before further damage occurs. It is a low-strain, non-destructive method and can be used to test any form of concrete or timber pile as well as drilled shafts, as long as they are not excessively slender. It can be used either for forensic examinations on existing piles or for quality assurance for new construction.
Various techniques can be used for interpreting the records of force and velocity taken under the impact of a light hammer blow. The most common technique is known as the transient dynamic response (TDR) method, which is both quick and cost-effective. Based on wave propagation theory, the top of a pile is struck with a hand-held hammer to generate a compression wave. This wave travels at a constant speed down the length of the pile and is measured with an accelerometer or geophone placed on top of the pile.
Any abnormalities or changes in cross-sectional area (e.g. due to the presence of a void) produce wave reflections which can be measured and mapped on a digitally-simulated profile of the pile.
While pile integrity testing can provide an indication as to the soundness of the pile, it does have some limitations. It cannot be used over pile caps and does not provide an indication of the pile’s bearing capacity. In addition, the test is not effective at evaluating the section of a pile below cracks that may cross the entire cross-sectional area of the pile.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.