Pile integrity test
Foundations provide support for structures, transferring their load to layers of soil or rock that have sufficient bearing capacity and suitable settlement characteristics to support them.
Pile foundations are deep foundations. They are formed by long, slender, columnar elements typically made from steel or reinforced concrete, or sometimes timber. A foundation is described as 'piled' when its depth is more than three times its breadth.
While the integrity of superstructure members can be tested and assessed from visual examinations, dimensions checks and so on, pile foundations, once they are in place, can be more difficult to test. Flaws and defects may develop during construction or subsequent excavation and trimming.
Pile integrity testing is used to discover and assess flaws before further damage occurs. It is a low-strain, non-destructive method and can be used to test any form of concrete or timber pile as well as drilled shafts, as long as they are not excessively slender. It can be used either for forensic examinations on existing piles or for quality assurance for new construction.
Various techniques can be used for interpreting the records of force and velocity taken under the impact of a light hammer blow. The most common technique is known as the transient dynamic response (TDR) method, which is both quick and cost-effective. Based on wave propagation theory, the top of a pile is struck with a hand-held hammer to generate a compression wave. This wave travels at a constant speed down the length of the pile and is measured with an accelerometer or geophone placed on top of the pile.
Any abnormalities or changes in cross-sectional area (e.g. due to the presence of a void) produce wave reflections which can be measured and mapped on a digitally-simulated profile of the pile.
While pile integrity testing can provide an indication as to the soundness of the pile, it does have some limitations. It cannot be used over pile caps and does not provide an indication of the pile’s bearing capacity. In addition, the test is not effective at evaluating the section of a pile below cracks that may cross the entire cross-sectional area of the pile.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.
Why construction can't afford to ignore the skills gap.